Reconstruction Olympic will manage in 2,184 mlrd griven

\"\"

On Tuesday, on November, 18th, the first deputy minister of regional development and building Anatoly Berkuta has sounded cost of works on reconstruction NSK Olympic.

According to the feasibility report (FEASIBILITY REPORT) of works on reconstruction National NSK Olympic cost of the given works is estimated in 2,184 mlrd grn, the first deputy minister of regional development and buildig Anatoly Berkuta has informed.

Thus the official has supported that stadium building was carried out Ukrainian genpodryadnoy by the company: "We are capable to construct this stadium. We have not one powerful stroykompaniya. And if me to ask - what? We have powerful company Kievgorstroj".

Among the companies which can take part in building of stadium, the Golden eagle also named Ukrmonolitspetsbud and Stalkonstruktsiyu.

Golden eagle has noticed, that for today on building of a roof of stadium there is some question and while there is no constructive decision. During too time, the Golden eagle has added, that roofing materials, and also, probably, designs which will support a roof, will not be domestic, and attraction of an order of 10 foreign experts can be necessary.

Besides, he has informed, that today it is necessary to solve some question with proprietors of the ground areas who are on ways of evacuation from stadium and in places for infrastructure development.

"It about 11 hectares and there five proprietors. We will confer, and to analyze all investdogovora. If all is lawful, all lawfully and will dare", - Anatoly Berkuta has noted.

The general contractor of building and reconstruction NSK Olympic should be defined on Wednesday, on November, 19th, at Cabinet session.


Shortly «Kievgorstroy» becomes general contractor NSK "Olympic".
Interdepartmental working group Minsemi and Minstroitelstva insists on definition “Kievgorstroy” the main contractor of reconstruction NSK "Olympic".It it has been declared Rostislavom Karandeevyim, the deputy minister on affairs of a family, youth and sports.He has informed that on November, 25th in Minseme session in which took part minister Jury Pavlenko and the first zamministr regional development and building has been...
Minregionstroy suggests to mortgage in the estimate of each object 10 % on acquisition of building engineering
The ministry of regional development and building suggests to mortgage in the estimate of each object 10 % on acquisition of building engineering. Deputy minister Minregionstroja Anatoly of the Golden eagle has informed on it today during general meeting Minregionstroya and Minprompolitiki. As he said, the majority of building engineering in Ukraine has become outdated and works much longer, than...
For preparation of Kiev for Euro-2012 it is planned to spend about 51,5 billion griven
All volume of a spadework to the European championship on football which will take place in 2012, will manage more than in 51,5 billion griven.The given information was informed by Anatoly Golubchenko who is the first vice-president of the Kiev city state administration.On football on all calculation it will be necessary to spend 51 billion 549 million 530 thousand fr...
The plan of reconstruction NSK "Olympic" will be accepted till November, 5th, then the tender for definition will follow
On October, 23rd state expert appraisal of the Ministry of regional development and building should express concerning the concept of the plan of reconstruction of National sport centre (in abbreviated form NSK) "Olympic" in the city of Kiev.The deputy minister on affairs of a family, youth and sports Sergey Drach at press conference which passed on Tuesday, has told, hat...
The London Olympic stadium by the end of 2012 can level with the earth
Representatives of the London management on development (LDA) have informed, that the stadium can be taken down right after Olympic games which will pass in the British capital in 2012....
"Olympic" will make glass walls
Stadium "Olympic" assort. German architectural company GMP which has won the tender for reconstruction has actively undertaken business. "At reconstruction two purposes – to save stadium as a historical instruction, after all it has been constructed in the twenties the last century, and to make of it a modern complex which becomes the Euro-12 symbol", – Alina Sotkovska has told...
Plans on reconstruction to Euro-2012 do not consider the further development of a city
Reconstruction of the National sports complex (NSK) "Olympic" and airport "Жуляны" in Kiev does not consider the further development of a city. In particular, in connection with reconstruction of stadium the city should load constantly the centre with transport and people - generalises opinion proektantov and town-planners the Interfax-Ukraine....
The concept of reconstruction NSK Olympic is definitively defined
Architectural bureau GMP from Germany has created the definitive project of reconstruction NSK Olympic. According to press-service Minsemi, Christian Hoffmann, the director of company GMP, on October, 10th in Kiev has given new i.o. General director NSK to Olympic Dmitry Chernyavsky the first folder of the design-budget documentation - the conceptual project which also is called as th feasibility report...
Euro-2012 arenas will cost to Ukraine of 700 million euro
Almost in 700 million euro building and reconstruction of football arenas on which there should pass Ukrainian part Evro-2012 will manage, informs the Sport express train.Reconstruction NSK Olympic in Kiev becomes the most expensive project. Cardinal updating of main arena of the European championship after which all 73 thousand spectator places will appear under a roof, will manage in 217...
Metallist it is planned to reconstruct by 2010
Reconstruction of all stadium Metallist where there will pass finishing games of the European championship on football of 2012, should be ended by December, 2010.The president of company DCH Alexander Yaroslavl has declared, that building terms are reduced by half a year. The stadium can contain 42 thousand fans of football, and all infrastructure will approach under UEFA standards....
In the Ukrainian village the stadium of the European sample is constructed
In village Golovkovka of the Alexandria area of the Kirovograd area opening ceremony of stadium of the European level to which while does not have analogues in all country has taken place. Event took place past Sunday, on October, 12th.The stadium contains in itself 500 spectators, also the sports complex and a training field adjoin to it. Building of the...
The centre of any city should be built up by underground, automated, ecologically pure parkings with protection system
On July, 23rd, 2008 under chairmanship of the deputy minister of Negody V. A meeting of Advice concerning building of parkings, garages and parking places has taken place at the Ministry of regional development and building of Ukraine. The question on ways and methods of the decision of a problem with maintenance of cities of Ukraine with necessary quantity of...
Milan in has got to an objective of the Arabian investors
The Prime minister of Italy Silvio Berlusconi past Friday has declared readiness of the Arabian investors to enclose nearby 20 mlrd euro to Milan – capital of the finance and a country fashion. In its opinion, investors from the United Arab Emirates and Qatar declare the intentions during the largest trade show of the world - Expo 2015. By estimations...